About the Edition

State Highway Departments and local street and road agencies are currently faced with aging highway systems and a need to extend the life of some of the pavements. The agency engineer should have the opportunity to explore the use of multiple surface types in the selection of a preferred rehabilitation strategy. This study was designed to look at the portland cement concrete overlay alternatives and especially the design of overlays for existing composite (portland cement and asphalt cement concrete) pavements.

Edition Notes

StatementJames K. Cable ... [et al.]
ContributionsCable, James K., 1941-, Iowa. Highway Research Board., United States. Federal Highway Administration., Iowa. Dept. of Transportation.
Classifications
LC ClassificationsTE278 .D524 2005
The Physical Object
Pagination1v. (various pagings) :
ID Numbers
Open LibraryOL16216725M
LC Control Number2006470002

Most of the rigid pavements constructed before the mid ’s did not include a tied concrete shoulder. Until , the AASHTO Guide for the Design of Pavement Structures did not consider or give credit for the inclusion of a tied concrete shoulder. Rarely were tied concrete shoulders incorporated in the pavement design. inhibit bond with the existing surface. Direct overlays of concrete over concrete will require that joints in the resurfacing match joint locations in the base pavements to prevent reflection cracks from occurring over these joints. The existing slab cannot have extensive surface distress and .   Addressing the interactions between the different design and construction variables and techniques this book illustrates best practices for constructing economical, long life concrete pavements. The book proceeds in much the same way as a pavement construction project. First, different alternatives for concrete pavement solutions are outlined. Unbonded CRCP overlay uses the same design procedure as new CRCP pavements. This use of unbonded CRCP overlay can be credited for contributing to the structural capacity of the existing concrete pavement and results in a thinner concrete pavement design than required for CRCP constructed on a new location.

Design and Construction Procedures for Concrete Overlay and Widening of Existing Pavements (TR, Project 6) Attributes of Good In-Service Concrete Pavements (Project 9) Rehabilitation of Concrete Pavements Utilizing Rubblization and Crack and Seat Methods (TR). APPENDIX A: INNOVATIONS AND STATE DOT DESIGN DETAILS Specifications for CRCP Temperature Management. Texas DOT Design Standards. Illinois DOT Design Standards. Composite Pavements. APPENDIX B: AASHTO/93 GUIDE REINFORCEMENT DESIGN Longitudinal Reinforcement Design Inputs. Concrete Tensile Strength. Concrete Coefficient of Thermal Expansion. Design and Construction Procedures for Concrete Overlay and Widening of Existing Pavements (TR, Proj. 6) Jun, Design and Construction of Continues Flight Auger Piles: $ OL Design and Construction of Safe Room and Shelter Against Terrorist Attack: $ OL Design and Construction Procedures for Concrete Overlay and Widening of Existing Pavements: $ OL Guidelines for Seismic Design of Tall Buildings: 8: $

  Procedures for rigid pavements can be found in Chapter Highway Design Manual July 1, (c Working Platform is a layer of granular base, asphalt, or concrete used to support construction equipment. A working platform permits the efficient construction of the Additional guidance and requirements on widening existing.   At times, concrete overlays can be used to rehabilitate asphalt pavements and existing concrete if damage has occurred. Concrete overlays are not effective for every situation though. For example, if the damage is due to distress because of the low quality of the materials that were used, then it usually isn’t worth the expense to complete an.

Design and construction procedures for concrete overlay and widening of existing pavements Download PDF EPUB FB2

Design and Construction Procedures for Concrete Overlay and Widening of Existing Pavements 5. Report Date September 6.

Performing Organization Code 7. Author(s) James K. Cable, Fouad S. Fanous, Halil Ceylan, Douglas Wood, Daniel Frentress, Toni Tabbert, Sun-Yoong Oh, Kasthurirangan Gopalakrishnan 8. Performing Organization Report No.

Existing design procedures for portland cement concrete overlays deal primarily with an existing asphaltic concrete pavement with an underlying granular base or stabilized base. This study reviewed those design methods and moved to the development of a design for overlays of composite pavements.

Bonded Concrete Overlay Software Programs Recommended Design Procedures (see previous page for links) 1.

Bonded Concrete Overlay on Asphalt (BCOA) Thickness Designer (ACPA ) 2. BCOA ME (Vandenbossche ) 3. Guide for Design of Pavement Structures. 4th ed. (AASHTO ) 4.

Mechanistic-Empirical Design Guide—A Manual of Practice File Size: 2MB. Design Traffic Thickness and condition of the existing pavement Construction convenience Economics Before implementing the overlay, the existing surface is to be corrected and brought to proper profile by filling pot holes, ruts and undulations No part of the overlay thickness shall not be used for the correction of surface Size: 1MB.

Guide to Concrete Overlays: Sustainable Solutions for Resurfacing and Rehabilitating Existing Pavements, 3rd Edition (Harrington and Fick ) The primary goal of this guide is to fill the knowledge gap about concrete overlays so that pavement owners can confidently include concrete overlays in their toolbox of pavement solutions and make moreFile Size: KB.

This design guide is designed to assist in the decision-making process concerning the widening of flexible pavements. It offers some recommended investigative and construction alternatives for widening given different case scenarios and should serve as a general guideline in that regard.

CRCP is the preferred concrete pavement type for new construction and concrete overlays for TI ≥ in all climate regions except High Mountain and High Desert. It may also be used for widening and replacement of existing lanes where there is adequate space to construct.

surfaces. It is the responsibility of the county engineer to make determinations regarding the design and maintenance of such roads and particularly for specific needs, such as weight restrictions. One method used by several counties in Minnesota is the construction of a bituminous-stabilized layer by adding several inches of new.

design procedures for hot-mix asphalt (HMA) overlay of rubblized PCC pavements, and design procedures for composite pavements.

A flowchart is presented in Chapter 54 (Figure A) that will assist in determining the. phases of a widening project. Pre-Design Evaluation Pavement widening requires a careful evaluation of the existing and proposed new widened pavement structures to ensure adequate performance under expected traffic loads, provide a consistent foundation across new and existing pavements, and perpetuate pavement drainage.

designed and constructed concrete overlays provide excellent performance, in many cases extending the life of existing pavements for an additional 30 years or more. Reasons to consider a concrete overlay solution include the following: 1.

Concrete overlays are not only a durable rehabilitation tool; they can also be a cost-effective maintenance. Thin whitetopping (TWT) is a 4- to 7-in. thick concrete overlay bonded to an existing asphalt concrete pavement (ACP) to create a composite section (see Figure ).

TWT is constructed normally at intersections where rutting and shoving in asphalt pavement continue to cause problems. of the design procedures, including new and rehabilitation pavement designs. The section on Geotechnical Design provides relevant routine geotechnical design information. The Deliverables and Report section ties all of the analysis and design together to ensure design recommendations are properly transferred to construction.

Evaluations of Existing Pavements • Evaluation is also used to determine: Required repairs where needed Establish the concrete overlay design thickness When combined with an overlay can the existing pavement help carry anticipated traffic as: an integrated part of the pavement (bonded) -or serve as a base or subbase (unbonded).

This second edition of Concrete Pavement Design, Construction, and Performance provides a solid foundation for pavement engineers seeking relevant and applicable design and construction instruction. It relies on general principles instead of specific ones, and incorporates illustrative case studies and prime design examples to highlight the material.

Construction Of Continuously Reinforced Continuously reinforced concrete pavements (CRCP) is a type of concrete pavement that does not require any transverse contraction joints. Transverse cracks are expected in the slab, usually at intervals of - 6 ft ( - m).

CRCP designs generally cost more than JPCP or JRCP designs initially due. Concrete Mix Design ♦ Bonded Concrete Overlay (BCO) Procedures This chapter provides a general overview of the equipment and procedures involved in the construction flexible pavements.

The equipment includes hot-mix plant operations, trucks, placement equipment, and. Decide whether the new concrete overlay is a bonded or unbonded system based on the existing conditions and pavement design inputs.

Use the Residual Strength Estimator tool to determine the FRC’s residual strength (f ) and effective flexural strength (f eff) (see Figure 3). Design the concrete overlay thickness in a pavement.

Bonded Concrete Overlays of Asphalt Pavements (BCOA) 5 2. Pre-Design Activities Once it is determined that the BCOA is a good rehab alternative, there are several pre-design activities that should be performed prior to designing the overlay.

These activities are described below. Gather Historical Records for Existing Pavement. Chapter 7: Flexible Pavement Rehabilitation Anchor: #i Section 1: Overview Anchor: #i Introduction.

Developing a rehabilitation design generally requires extensive investigation into the condition of the existing pavement structure, performance history, and laboratory testing of materials to establish suitability of existing and proposed materials for use in the.

The nominated design subgrade CBR for the widening may be lower than that of the existing pavement given the likelihood of pneumatic conditioning of the existing subgrade under extended traffic The traffic loading may have increased since the date of the construction of the existing pavement, resulting in an increased pavement thickness.

If the steel serves its proper function and keeps cracks from widening, aggregate interlock is preserved and concrete stresses in the concrete slab due to traffic loading are reduced.

The CRCP thickness design is detailed in Section 2, Approved Design Method, and Section 3, Rigid Pavement Design Process for CRCP. Concrete Pavements, Design and Construction of Johts for Concrete Streets, and Suggested Specifications for Construction of Concrete Streets, discuss the subjects of subgrades and subbases, jointing practices, and specifications in much greater detail, Following are the factors involved in the design process for concrete streets: 1.

Subgrades. Pavements are designed for an expected service life or design life. In some parts of the United Kingdom the standard design life is 40 years for new bitumen and concrete pavement. Maintenance is considered in the whole life cost of the road with service at 10, 20 and 30 year milestones.

Highway Design Manual July 1, Concrete Over Asphalt Composite Pavement Because of the minimum foot thickness requirements for concrete surface course, all pavements with concrete surface course are engineered according to the standards and procedures for rigid pavements in Chapter Topic – Engineering Criteria.

Design and detailing of joints is important for these pavements. All three conventional pavement types have been used as overlays, although jointed plain overlays are most common. Prestressed and precast concrete pavements are used for similar applications as conventional concrete pavements, but have been used infrequently.

addresses the design and construction of jointing sys­ tems for concrete street pavements. Two other ACPA publications, Design of Concrete Pavements for City Streets and Subgrades and Subbases for Concrete Pave­ ments, address city street thickness design and subgrade/ subbase preparation.

Typically street pavement slabs range from 5 to 8 in. Get this from a library. Flexible pavement overlay design procedures. [United States. Federal Highway Administration. Structures and Applied Mechanics Division.; Resource International.;] -- A review and evaluation of existing flexible pavement overlay design procedures, including the ARE procedure (FHWA Contract DOT-FH) resulted in a fully computerized rational method for the.

Development of design guide for thin and ultra-thin concrete overlays of existing asphalt pavements. Task 2: Review and selection of structural response and performance models. MN/RC Google Scholar. Concrete Pavement Design, Construction and Performance In some cases, however, design or construction errors or poorly selected materials have considerably reduced pavement life.

It is therefore impor-tant for pavement engineers to understand materials selection, mixture proportioning, design and detailing, drainage, construction techniques. Design and Construction Procedures for Concrete Overlay.existing and widening sect Ions will be structurally adequate.

Many lane widening projects have developed serious deterioration along the longitudinal joint due to improper design. The key design recommendations are as follows: (1) (2) (3) The design ives of both the overlay and the new widening construction should be the same to avoid the.pavement widening including shoulders, HMA overlays of rigid pavements, bonded concrete overlays on rigid pavements, or thin whitetopping of flexible pavements.

Completing Pavement Design Report: Follow procedures outlined in Table